Choose original planned hours

Why ask this?

A project lead reviewing staffing needs to choose the applicable plan before comparing actual and planned hours for each team.

Start with the sample data

Open source.csv. In the first row of source.csv, Cell = Green, Used hours = 8, Original planned hours = 6, Revised planned hours = 5.

What to say

Please show a bar chart of net variance by cell. Add up used hours and planned hours by cell first, then subtract plan from used. Keep positive, negative and zero cells.

Processing time

Recorded audio to chart ready
7.86 s
Transcript to chart ready
0.63 ms

One local replay from recorded audio through transcription and native chart data preparation. Includes processing of the clarification and reply. Time waiting for a person to answer is excluded. Recording time and screen painting are excluded.

See the transcript in the composerRecorded transcript entered in the native composer
What n0is transcribed

Please show a bar chart of net variance by cell. Add up used hours and planned hours by cell first, then subtract plan from used. Keep positive, negative, and zero cells.

When n0is asks

Which column should I subtract?

Original planned hours.

How the canvas produces the result

  1. CSV Input · Read the sample records

    source.csv supplies 2 rows. These records are the inputs to the next step.

  2. Aggregate · Sum Used hours, Sum Original planned hours for each Cell

    If a category appears more than once, its records contribute to one result. The first output row contains Cell = Green, sum_Used hours = 8, sum_Original planned hours = 6.

  3. Math · Calculate Net variance

    Apply [sum_Used hours] - ([sum_Original planned hours]) to each input row. The first row yields 2.

  4. Charts · Draw the bar chart

    Use Cell for the categories and Net variance for the plotted values.

Canvas review in progress for Math. The recording verifies the result. Rebuilding these steps from the left panel still needs verification.

Native n0is canvas for Choose original planned hours

The chart

Workflow result in n0is
CellNet variance
Green2
Red-1

How to use the result

For Cell Green, the sample reports Net variance of 2.